Construction Schedule

LaSalle Trail Construction Schedule


(Subject to Change)

Phase I


Cleveland Road to Darden Road


  • Design and Engineering - 2014-2015
  • Let for Construction December 9, 2015, contract awarded to Walsh and Kelly Inc.

Phase II


Darden Road to Auten Road


  • Design and Engineering - 2015-2016
  • Let for Construction April 1, 2017, contract awarded to Selge Construction Co, Inc.

Phase III


Auten Road to State Line Road


  • Design and Engineering - 2015-2017
  • Construction - 2017-2018
Lasalle Trail Funding Map